Plant type:

2x steam boilers 20 MW with 2x gas burner each

Installation site:

Dörpen Germany

Control

Electronic compound control with classic controller

Plant type:

10 MW steam boiler with an oil/gas burner and a 200 KW burner for the biogas accumulating during production

Installation site:

Neuss, Germany

Control

Failsafe PLC with operating unit including controller, electronic compound, link to control system

Plant type:

Supervision-free operation with burner control

Installation site:

Graz, Austria

Control

Failsafe PLC with operating unit including Supervision-free operation and controllers 1 x electronic compound

 

Plant type:

Burner control

Installation site:

Salzgitter, Germany

Control

Failsafe S7 300 PLC for multi-burner control

Plant type:

Boiler control

Installation site:

Ponsfeld, Germany

Control

Failsafe S7-300 PLC with visualisation for the boiler control, linked via Profinet to external periphery and via DP-Bus with the frequency converter and the electronic burner control

 

Plant type:

3x hot water boilers 20 MW and 2x oil/gas burners each

Installation site:

Fürth Germany

Control

Non-failsafe PLC with operating unit including controller, electronic compound, boiler sequence controller

Plant type:

Boiler control for a steam boiler

Installation site:

Nontrach Vietnam

Control

The project entailed the planning and construction of the control cabinet as well as the programming of the failsafe S7-300 PLC and the visualisation of boiler control, linked to the electronic compound control via DP bus

Plant type:

Boiler control for a 55 MW hot water boiler with two oil/gas burners

Installation site:

Kassel, Germany

Control

The project entailed the planning and construction of the control and power cabinets, the programming and visualisation of the T3000 control system as well as complete electrical installation on site

Plant type:

Combined cycle plant

Installation site:

Duenas, Spain

Control

Failsafe, high availability S7-400 PLC with visualisation of auxiliary combustion and boiler control of a gas turbine’s heat recovery boiler. The control cabinet in the field level is connected to the two CPUs via Profisafe. In addition to the creation of wiring diagrams and automation, engineering services included the preparation of logic diagrams for the control system.

Plant type:

Drying plant for dairy products

Installation site:

Altentreptow, Germany

Control

Replacement of the existing burner control with a failsafe S7-300 PLC with visualisation via PT 177B

Plant type:

Burner control

Installation site:

Linz, Austria

Control

Failsafe PLC

Plant type:

2x Supervision-free operation with burner control

Installation site:

Mitterdorf im Mürztal, Austria

Control

Failsafe PLC with operating unit including Supervision-free operation for two steam boilers 2x electronic compound

Plant type:

7x hot water boilers 40-180 MW and 6x oil/gas burners each

Installation site:

Vienna, Austria

Control

Failsafe PLC with operating unit, mechanical compound, link to TXP

Plant type:

Auxiliary combustion for a heat recovery boiler of a 6 MW gas turbine and 6 gas burners

Installation site:

Erlangen, Germany

Control

Failsafe, redundant PLC [CPU417FH] with PSC7 and link to control system

Anlagentyp:

2x drier 1.5MW each 1x gas burner

1x steam boiler 10MW 1x gas burner

Installation site:

Iphofen Germany

Control

Failsafe PLC with visualisation, electronic compound, link to control system

Failsafe PLC with visualisation, electronic compound, link to control system

Plant type:

2x driers 1.5 MW each 1x gas burner

Installation site:

Rottleberode Germany

Control

Failsafe PLC with visualisation including compound control, link to control system

Plant type:

4x combustion chambers, 10 MW each and 1x gas/oil and coal dust burner each

Installation site:

Rottleberode, Germany

Control

Failsafe PLC with visualisation, electronic compound, link to control system

Plant type:

4x steam boilers 5 MW each and 1x oil/gas burner each

Installation site:

Braunschweig Germany

Control

PLC with visualisation including controller, electronic compound

Plant type:

1x steam boiler 10 MW with 2x oil burners

Installation site:

Flensburg Germany

Control

Non-failsafe PLC with operating unit, electronic compound, classic controller, link to PCS7

Plant type:

Boiler Control

Installation site:

Hannover, Germany

Control

The project entailed a modification and the commissioning on-site, the planning was done with EPLAN P8, also included the programming of the failsafe S7-1500 PLC and the visualisation by Siemens TIA Portal

Plant type:

Burnercontrol

Installation site:

Sisseln, Switzerland

Control

The project entailed the construction of the control cabinet and the on-site assembly.